Asbestos Reassessment Inspections, January 8, 2018-March 9, 2018, 4:45pm-7:00am

December 2017

 

November 2017

REVISED: Erie Hall/Leddy Library (East) Main Building-Banners Replacement, November 21, 2017, 8:00am-5:00pm

Biology Building-Emergency Steam Repair, November 18, 2017, 6:00am-12:00pm

Biology Building-Guard Railing Installation, November 20-24, 2017, 7:00am-5:00pm

Chrysler Hall North-Renovations Area Update, November 20-December 8, 2017, 8:00am-4:30pm

Biology Building-Partial Electrical Shutdown, November 19, 2017, 7:00am-4:00pm

Biology Building-Domestic Hot and Cold Water Shutdown, November 18, 2017, 7:00am-4:00pm

Education Building-Electrical Work for Door Actuators, November 20, 2017, 8:00am-12:00pm

Pitt Ferry Building-Irrigation System Winterization, November 17, 2017, 12:00pm-5:00pm

Erie Hall/Leddy Library (East) Main Building-Banners Replacement, November 17, 2017, 8:00am-5:00pm

REVISED: Chrysler Hall North-Type 2 Removal of Plaster Window Bulkheads, November 13-15, 2017, 9:00am-5:00pm

Pitt Ferry Building-Emergency Generator & Lighting Inspections and Testing, November 17, 2017, 8:00am-12:00pm

Lambton Tower-Installation of Pre-Fabricated Walls, November 16-17, 2017, 8:30am-4:30pm

Chrysler Hall North-Type 2 Removal of Plaster Window Bulkheads, November 13-14, 2017, 9:00am-5:00pm

Vanier Hall-Power and Data Installation, November 15-December 15, 2017, 8:00am-5:00pm

CAW Student Centre/Human Kinetics-Service Tunnel and Loading Dock Repairs, November 13, 2017-January 8, 2018

REVISED: Centre for English Language Development-Walk-thru to Identify Fire Alarm Devices, November 14, 2017, 8:30am-4:00pm

REVISED: Maintenance Building-Walk-thru to Identify Fire Alarm Devices, November 16, 2017, 8:30am-4:00pm

REVISED: Campus Wide-Roof Condition Assessments-November 9, 2017 to April 1, 2018

REVISED: Human Kinetics/Field House-Roof Repairs, November 13-December 20, 2017

Assumption Hall-Contractor Site Review, November 9, 2017, 1:00pm-2:00pm

Assumption Hall-Walkways and Railings Installations, November 7-December 22, 2017, 8:00am-5:00pm

Lambton Tower/Erie Hall-Domestic Cold Water Shutdown, November 4, 2017, 8:00am-12:00pm

Great Lakes Institute of Environmental Research-Fire Alarm Shutdown, November 2, 2017, 8:00am-4:00pm

Assumption Hall-Contractor Site Review, November 2, 2017, 10:00am-11:00am

Chrysler Hall North-Painting of Rooms and Corridors, November 2-December 1, 2017, 8:00am-4:30pm

Campus Wide-Roof Condition Assessments-November 1, 2017 to April 1, 2018

Asbestos Reassessment Inspections, November 6, 2017-March 20, 2018, 8:00am-8:00pm

Human Kinetics-Roof Repairs, November 1-22, 2017, 7:00am-7:00pm

October 2017

DATE REVISED: Centre for Engineering Innovation-Walk-thru to Identify Fire Alarm Devices, October 30-31, 2017, 8:30am-4:00pm

Odette School of Business-Water Shutdown Due to New Water Booster Pump Installation, October 28, 2017, 6:00am-2:00pm

Human Kinetics/Field House-Roof Repairs, Aggregate Removal, October 19-20, 2017, 7:00am-5:00pm

Psychology Centre-Demolition of Existing Building at 326 Sunset Avenue, October 23-November 3, 2017, 7:00am-5:00pm

Human Kinetics-Main Entrance Removal and Reseal of Caulking, October 21, 2017, 8:00am-4:00pm

Pitt Ferry Building-Emergency Generator & Lighting Inspections and Testing, October 20, 2017, 8:00am-12:00pm

Erie Hall-Computer Science Lab 3127 Upgrades, October 17-November 3, 2017, 7:00am-5:00pm

Alumni Hall-Roof Repairs, October 17-November 30, 2017, 8:00am-5:00pm

Centre for Engineering Innovation-Walk-thru to Identify Fire Alarm Devices, October 23-24, 2017, 8:30am-4:00pm

Maintenance Building-Walk-thru to Identify Fire Alarm Devices, October 20, 2017, 8:30am-4:00pm

Centre for English Language Development-Walk-thru to Identify Fire Alarm Devices, October 17, 2017, 8:30am-4:00pm

Biology Building-Main Entrance Lobby-Accessibility Lift Upgrades, October 16-November 10, 2017, 8:00am-4:30pm

Laurier Hall-Valve Repair and Switch Over, October 17-20, 2017, 6:00am-4:00pm

Campus Wide - Switch from Cooling Mode to Heating Mode, October 23 - November 6, 2017, 12:00pm - 10:00am

CAW Student Centre-Wireless Door Module Installations, October 13, 2017, 8:00am-4:00pm

Biology Building-Emergency Repair - Steam Shutdown, October 13, 2017, 6:00am-2:00pm

Memorial Hall-Emergency Repair - Steam Shutdown, October 12, 2017, 6:00am-2:00pm

Odette School of Business-Main Elevator Out of Service, October 11-13, 2017, 4:30pm-4:30pm

Library Main and West Building -Fire Alarm System Upgrades, October 12, 2017 to February 7, 2018

Energy Conversion Centre-Roof Replacement/Aggregate Removal, October 12, 2017, 7:00am-4:30pm

Parking Garage-East Elevator Back In Service, October 10, 2017

Parking Garage- Elevators Out of Service Until Further Notice, October 10, 2017

Health Education Building/Education Building-Electrical Work for Door Actuators, October 10-13, 2017, 8:00am-4:00pm

Biology Building/Chrysler Hall South-Electrical Work for Stage 4, October 10-17, 7:00am-5:00pm

Alumni Hall-Venting System Repairs, October 4, 2017, 10:00am-2:00pm

Vanier Hall-Roof Replacement/HVAC Shutdown, October 10-12, 2017, 7:30am-7:30am

Chrysler Hall South-Classrooms 51 and 53 AV Installations, October 6-15, 2017, 8:00am-5:00pm

Chrysler Hall North/South/Tower, Electrical Work for Door Actuators, October 2-3, 2017, 8:00am-4:00pm

Main Campus Quad-Installation of Campus Walkway Lighting, October 2-5, 2017, 7:00am-5:00pm

September 2017

Science and Research Innovation Facility (SRIF) -Abatement in North/West Areas, September 28, 2017, 3:00pm-5:00pm

Human Kinetics, Front Entrance Door Repairs, September 29, 2017, 8:00am-5:00pm 

Lambton Tower/Erie Hall-Room 1110-1112 Upgrades, September 26-29, 2017, 8:00am-5:00pm

Campus Commons Area (East and West Ends of Angled Walkway)-Signs Installation, September 27, 2017, 7:00am-5:00pm

Alumni Hall-Venting System Repairs, September 26-27, 2017, 6:00am-2:00pm

Human Kinetics-Electrical Work for Door Actuators, September 22, 2017, 8:00am-4:00pm

Parking Garage Repairs, September 21-22, 2017, 8:00am-7:00pm

Pitt Ferry Building-Emergency Generator & Lighting Inspections and Testing, September 22, 2017, 8:00am-12:00pm

Education Building-Mold Remediation Room 1127, September 19-21, 2017, 8:00am-5:00pm

Medical Education Building-Hot Water Shutdown Due to Steam Main Repairs, September 19-20, 2017, 6:00am-2:00pm

REVISED: Science and Research Innovation Facility (SRIF)-HVAC Shutdown/Asbestos Abatement Type III, September 15-18, 2017, 10:00am to 12:00pm

Leddy Library (West Wing and East Main), Installation of Wiring and Equipment for Enhanced Cell Coverage, September 15-October 18, 2017, 10:00pm-7:00am

Biology Building-Main Entrance Lobby - Accessibility Upgrades, September 14-November 7, 2017, 8:00am-4:30pm

Periodic Closure of Seating Pods Along Turtle Island Walk-September 18-20, 2017, 7:00am-5:00pm

Education Building-Lower Roof Replacement, September 16-17, 2017, 8:30am-4:30pm

Essex Hall-Power and Data Outlet Installation, September 14-15, 2017, 8:00am-5:00pm

Science and Research Innovation Facility (SRIF)-HVAC Shutdown/Asbestos Abatement Type III, September 15-18, 2017, 12:00pm to 12:00pm

Leddy Library (East) Main Building-Elevator Out of Service, September 11-12, 2017, 8:00am-4:00pm

Human Kinetics-Flow Switch Replacement, September 12, 2017, 6:00am-2:00pm

Alumni Hall-Control Valve Replacement, September 12, 2017, 7:00am-2:00pm

Parking Lot Line Painting, September 8-10, 2017, 6:00am-3:00pm

LeBel Building/Music Building-Tile Replacement and Paint Work, September 1-4, 2017, 4:30pm-7:00pm

Lambton Tower-Electrical Work, September 6, 2017, 8:30am-4:00pm

Vanier Hall-Roof Replacement, September 7-November 3, 2017, 7:00am-7:00pm

August 2017

LeBel Building-Replace Ceiling Tiles, August 31-September 1, 2017, 8:00am-5:00pm

Odette School of Business-Hot Water Booster Pump Replacement, August 29-30, 2017, 8:00am-4:00pm

Education Building-Roof Replacement Ph2, August 28-September 30, 2017, 8:30am-4:30pm

Law Building-Fire Alarm Shutdown for Door Hardware Upgrades, August 29, 2017, 8:30am-10:30am

Vanier Hall-Repair Heaving Floor Tiles, August 28-30, 2017, 9:30am-4:30pm

Dillon Hall/Leddy Library (West Wing)/Alumni Hall/Cartier Hall- Power Outage-August 29-31, 2017, 12:00am-8:00am

Essex Hall-Fumehood Control Valve Replacement, August 29-31, 2017, 7:00am-2:00pm

Human Kinetics-Valve and Coil Replacement, August 29-31, 2017, 7:00am-2:00pm

Turtle Island Walkway-Aluminum Flag Installations, August 29, 2017, 8:00am-5:00pm

Assumption Hall-Roof Replacement, West Face, August 28 - September 29, 2017, 8:30am-4:30pm

DATE EXTENDED: Education Building-Roof Replacement Ph1, Aggregate Removal, August 28 - September 1, 2017, 8:30am-4:30pm

Chrysler Hall North-Air Conditioning Shutdown, August 28-31, 2017, 7:00am-4:30pm

REVISED: Assumption Hall/Dillon Hall/Odette School of Business-Thermo-graphic Drone Scanning of Building Walls, August 23-24, 2017, 7:30am-7:00pm

Assumption Hall-Barrier Free Access Ramp Installation, August 28-October 25, 2017, 8:00am-5:00pm

Education Building-Roof Replacement, August 28, 2017, 8:30am-4:30pm

Assumption Hall/Dillon Hall/Odette School of Business-Thermo-graphic Drone Scanning of Building Walls, August 23-24, 2017, 5:00pm-12:00am

Biology Building-East Side Angled Walkway Renovation, August 28-September 1, 2017, 7:00am-5:00pm

Chrysler Hall South-Electrical Feeds Installation, August 24-September 8, 2017, 7:00am-5:00pm

Emergency Water Shutdown-August 18, 2017, 11:00am-5:00pm

DATE EXTENSION: Installation of Signs and Sign Bases-August 26-September 1, 2017, 7:00am-5:00pm

Chrysler Hall South/Biology Building/Education Building-Wall Damage Repair and Replace Ceiling Tiles, August 18-21, 2017, 8:00am-5:00pm

Chrysler Hall South-Temporary Closure of Corridor on Lower Level, August 18-25, 2017, 7:00am-11:00pm

Education Building-Stair Delineation Installation, August 18, 2017, 7:00am-5:00pm

Lambton Tower-Removal of Concrete Floor By East Entrance, August 17, 2017, 8:00am-5:00pm

Pitt Ferry Building-Emergency Generator & Lighting Inspections and Testing, August 31, 2017, 8:00am-12:00pm

Chrysler Hall North/Lambton Tower-Elevator Disruption Due to Economics Department Move, August 17-22, 2017, 9:00am-4:00pm

Education Building-Electrical Work for Door Actuators, August 15-16, 2017, 8:00am-4:00pm

Chrysler Hall North/Chrysler Hall South/Chrysler Hall Tower-Electrical Work for Door Actuators, August 15-22, 2017, 8:00am-4:00pm

Fire Alarm Operations and Verifications, August 14-18, 2017, 7:00am-4:00pm

Main Quad-Outside Lighting Installation, August 15-18, 2017, 8:00am-5:00pm

Dillon Hall-Lower Level Renovations, August 23-December 1, 2017, 7:00am-3:30pm

Campus Parking Lot Repairs, August 8-14, 2017, 8:00am-6:

Biology Building-Closure of Accessible Ramp, August 8-10, 2017, 7:00am-5:00pm

Science and Research Innovation Facility (SRIF) Project-Cutting An Opening in the Service Tunnel Wall, August 8-10, 2017, 7:00am-7:00pm

Alumni Hall - Exterior Masonry Repairs, August 8-September 8, 2017, 7:00am-5:00pm

July 2017

Law Building-Door Hardware and Accessibility Upgrades, August 4, 2017, 8:30am-10:00am

DATE EXTENSION: Chrysler Hall South and North-Replace Ceiling Tiles, July 28-August 2, 2017, 9:00am-7:00pm

DATE EXTENSION: Memorial Hall/Education Building-Ceiling Tiles Replacement, July 26-August 3, 2017, 10:00am-7:00pm

DATE EXTENSION: Biology Building-Ceiling Tiles Replacement, July 27-August 3, 2017, 11:00am-7:00pm

Human Kinetics-Electrical Work for Door Actuators, August 2-16, 2017, 8:00am-4:00pm

CANCELLED: Lambton Tower-Fire Alarm Shutdown, July 29, 2017, 8:00am-4:00pm

Biology Building-Ceiling Tiles Replacement, July 27-28, 2017, 11:00am-7:00pm

ABATEMENT POSTPONED: Science and Research Innovation Facility (SRIF) Project - Type III Abatement in North/West Areas of Essex Hall, July 28-August 18, 2017, 7:00am-5:30pm

DATE ADJUSTMENT: Great Lakes Institute of Environmental Research-No Air Conditioning, July 28-30, 2017, 6:00am-4:00pm

Chrysler Hall South-Replace Ceiling Tiles, July 28, 2017, 9:00am-5:00pm

Biology Building-Ceiling Tiles Replacement, July 27, 2017, 11:00am-7:00pm

Memorial Hall/Education Building-Ceiling Tiles Replacement, July 26, 2017, 10:00am-7:00pm

DATE EXTENSION: Science and Research Innovation Facility (SRIF) Project – Construction of Tunnel Connection, June 21 - August 17, 2017, 7:00am-6:00pm

Fire Alarm Operations and Verifications, August 8-11, 2017, 7:00am-4:00pm

Fire Alarm Operations and Verifications, July 31-August 4, 2017, 7:00am-4:00pm

Campus Roofing Upgrades-Contractor Pre-Bid Walk-Thru, July 26, 2017, 9:00am-1:00pm

Pitt Ferry Building-West Side Exterior Gate Painting, July 24-25, 2017, 8:00am-5:00pm

Pitt Ferry Building-Centre Stairwell Repairs, July 24, 2017, 7:00am-1:00pm

Chrysler Hall South-Abatement in Classrooms 51, 53 and Corridor, July 27-29, 2017, 3:00pm-11:00pm

Installation of Signs and Sign Bases-July 26-August 25, 2017, 6:00am-6:00pm

Inspection and Testing of High Voltage Cables in Tunnels-July 26-28, 2017, 8:00am-3:00pm

CANCELLED: Energy Conversion Centre/Cogeneration Unit-Power Outage-July 31, 2017, 9:00am-12:00pm

Power Outage-July 30, 2017, 8:00am-12:00pm

CANCELLED: Vanier Hall-Domestic Water System Shutdown, July 25, 2017, 4:00pm-8:00pm

MacDonald Hall/Laurier Hall-Patching and Painting, July 26-August 15, 2017, 8:00am-4:30pm

University Computer Centre-Fire Alarm Operations and Verifications, July 24, 2017, 7:00am-8:00am

Biology Building-Water Shutdown for Backflow Preventer Installation, July 29, 2017, 7:00am-5:00pm

Chrysler Hall Tower Complex-Faulty Water Meter Replacement, July 18, 2017, 9:45am-3:00pm

CAW Student Centre-Painting Student Health Services, July 17-28, 2017, 3:30pm-11:59pm

Pitt Ferry Building-Emergency Generator & Lighting Inspections and Testing, July 21, 2017, 8:00am-12:00pm

Alumni Hall-Interior Repairs and Painting, July 18-September 1, 2017, 7:00am-6:00pm

Odette School of Business-Lower Level Women’s Washroom Shutdown, July 17, 2017, 7:00am-6:00pm

Assumption Hall-Air Conditioning Unit Shutdown for Repairs, July 13-20, 2017, 8:30am-4:30pm

Research Innovation Facility (SRIF) Project – Essex Hall Connection to SRIF, July 7-August 25, 2017, 7:00am-6:00pm

Chrysler Hall South-Classroom Renovations, July 17-September 1, 2017, 8:00am-5:00pm

Clark Lot (Formerly Lot 'V')-Tree Removal, July 11, 2017, 9:00am-3:30pm

Campus Wide - Emergency Generator Testing, July 17-21, 2017, 8:00am-5:00pm

Chrysler Hall Tower-Water Shutdown to Repair Leaks and Service Valves, July 12, 2017, 4:30pm-10:00pm

Science and Research Innovation Facility (SRIF) Project – Asbestos Type II Abatement, July 15-16, 2017, 7:00am-4:30pm

Lambton Tower-Painting and Flooring Work on 6th and 7th Floors, July 10-31, 2017, 7:30am-4:00pm

Lambton Tower-Access to Ceiling Space on 5th Floor to Cap-off Ductwork, July 8, 2017, 7:00am-3:30pm

Parking Lot Q-Periodic Closure of the West Entrance (Sunset Avenue), July 12-21, 2017, 7:00am-5:00pm

Centre for Engineering Innovation-Installation of Roof Pavers, July 7-21, 2017, 8:30am-4:30pm

Facilities Condition Assessment with VFA, July 4-7, 2017, 7:00am-4:00pm

Fire Alarm Operations and Verifications, July 24-28, 2017, 7:00am-4:00pm

Fire Alarm Operations and Verifications, July 17-21, 2017, 7:00am-4:00pm

Centre for Engineering Innovation-Tree Trimming, July 7, 2017, 7:00am-3:30pm

Fire Alarm Operations and Verifications, July 10-14, 2017, 7:00am-4:00pm

Assumption Hall-Cleaning and Maintenance of Air Conditioning Units, July 4-11, 2017, 8:30am-4:30pm

Fire Alarm Operations and Verifications, July 4-7, 2017, 7:00am-4:00pm

Chrysler Hall South-Type 2 Enclosure, July 6, 2017, 7:00am-5:00pm

Vanier Hall/Cartier Hall-Vanier Circle Repaving, July 4-August 21, 2017, 8:00am-6:00pm

June 2017

Memorial Hall-Removal of Ivy from Building, July 3-14, 2017, 7:00am-4:00pm

Pitt Ferry Building-Outside Wall Inspection, June 28, 2017, 6:00am-2:00pm

Assumption Hall-Contractors Site Visit and Tour, June 27, 2017, 11:30am-12:30pm

St. Denis Fieldhouse-Cooling Tower Repair, June 26, 2017, 7:30am-3:00pm

Lambton Tower-Steam Coil Removal, June 26, 2017, 7:30am-3:00pm

Alumni Hall-No Hot Water for the Day, June 26, 2017, 7:30am-3:00pm

Science and Research Innovation Facility (SRIF) Project – Emergency Watermain Shutdown, June 22, 2017, 5:30pm-10:30pm

DATE REVISED: Lambton Tower-Cap-off Ductwork on 6th Floor, June 24, 2017, 7:00am-3:30pm

Essex Hall/CAW Student Centre-Installation of Emergency Telephone in Elevator, June 22, 2017, 9:00am-5:00pm

Parking Garage-Replace Door on Level 7A, June 27, 2017, 8:30am-4:00pm

Human Kinetics-Door Closer Replacement, June 21, 2017, 9:00am-12:00pm

Memorial Hall/Dillon Hall/Chrysler Hall South/Essex Hall-Door Hardware Replacement, June 21, 2017, 8:30am-3:30pm

REVISED: University Computer Centre/Education Gym-Building Walk-Thru to Identify Fire Alarm Devices, June 27-29, 2017, 9:00am-4:00pm

Dillon Hall-HVAC Repair, June 19-22, 2017, 6:00am-2:00pm 

REVISED: Science and Research Innovation Facility (SRIF) Project – Construction of Tunnel Connection, June 21 - July 21, 2017, 7:00am-6:00pm

Pitt Ferry Building-Outside Wall Inspection, June 20, 2017, 6:00am-2:00pm

Lambton Tower-Cap-off Ductwork on 6th Floor, June 20-21, 2017, 8:00am-4:00pm

All Campus Buildings-Emergency No Steam or Chilled Water Until Further Notice 

University Computer Centre/Education Gym-Building Walk-Thru to Identify Fire Alarm Devices, June 20-22, 2017, 9:00am-4:00pm

CAW Student Centre-Installation of Emergency Phone in Elevator, June 14, 2017, 7:00am-6:00pm

Science and Research Innovation Facility (SRIF) Project – Construction of Tunnel Connection, June 23 - August 11, 2017, 7:00am-6:00pm

Science and Research Innovation Facility (SRIF) Project – Essex Hall Connection to SRIF, June 19 - Agusut 25, 2017, 7:00am-6:00pm

Essex Hall-Shutdown of HV8, June 13, 2017, 6:00am-10:00am

Chrysler Hall Tower/University Computer Centre-Pedestrian Walkway and Stair Repair, June 14-17, 2017, 7:00am-7:00pm

Education Building-Electrical Breaker Replacement, June 11, 2017, 7:00am-10:00am

Odette School of Business-Leak Repairs at Penthouse, June 8-9, 2017, 8:00am-5:00pm

Service Tunnels-Installation of Storm Sumps Upgrades, June 12-July 30, 2017, 7:00am-7:00am

Human Kinetics-Ceiling Mounted Backstops Installation Through-out Fieldhouse, June 12-23, 2017, 8:00am-5:00pm

Essex Hall-Painting of Room B88-1 and Adjacent Office, June 7-9, 2017, 7:00am-2:00pm

Education Building-Main Entrance, Card Access Out-of-Service Until Further Notice, June 6-August 18, 2017, 12:00am-11:59pm

Centre for English Language Development-Weather Sealing Air Conditioning Unit, June 8-9, 2017, 8:00am-4:00pm

Domestic Hot Water Shutdown-June 9-12, 2017, 9:00am-8:00am

Essex Hall-Domestic Hot Water System Flush, June 9-12, 2017, 2:00pm-8:00am

Odette School of Business-Classroom 104 Renovations, June 9-September 1, 2017, 8:00am-5:00pm

Pitt Ferry Building-Emergency Generator and Lighting Inspections, June 22, 2017, 8:00am-12:00pm

Law Building-Building Walk-Thru to Identify Fire Alarm Devices, June 13-15, 2017, 9:00am-4:00pm

REVISED: Campus Wide Power Outage, June 17, 2017, 6:00am - 6:00pm

Campus Wide Steam Outage, June 16-18, 2017, 12:00pm - 10:00pm

May 2017

Centre for Engineering Innovation-Roof Cleaning, May 23, 2017, 8:00am-4:00pm

Science and Research Innovation Facility (SRIF) Project – Emergency Water Main Repair, May 16, 2017, 4:30pm-11:59pm

Psychology Centre- 336, 348 and 326 Sunset Avenue, May 23-June 30, 2017, 7:00am-5:00pm

Education Building-Replace Door Hardware, May 17-18, 2017, 9:00am-7:00pm

Lambton Tower-Filter Element Replacement, May 22-26, 2017, 6:00am-4:00pm

Vanier Hall-Domestic Hot Water Shutdown, May 9-23, 2017

Laurier Hall/Vanier Hall-Building Walk-thru to Idendifty Fire Alarm Devices, May 16-18, 2017, 9:00am-4:00pm

Facilities Condition Assessment with VFA, May 23-June 2, 2017, 7:00am-4:00pm

Human Kinetics-Flush Hot Water System, May 9-12, 2017, 1:00pm-11:59pm

Leddy Library West Wing-Asbestos Abatement and Valve Removal, May 10, 2017, 6:00am-2:00pm

West Side of Patricia Avenue, South Side of the New Gate-Installation of New Landscaping Bed-May 15-19, 2017, 7:00am-5:00pm

Essex Hall-Shutdown of Airhandling Unit (HV8), May 9, 2017, 7:00am-10:00am

Chrysler Hall North-Camera Mount Installations in Rooms 1103 and 1107 with Type II Asbestos Abatement Procedures, May 9, 2017, 8:30am-12:00pm

Assumption Church Parking Lot Closed for Line Painting-May 7, 2017, 7:00am-1:00pm

DATE EXTENSION: Chrysler Hall South-Temporary Closure of Northwest Building Exit, May 1-12, 2017, 8:00am-4:00pm

Science and Research Innovation Facility (SRIF) Project – Traffic Interruption at Essex Hall Delivery Access Road, May 15, 2017, 6:00am-6:00pm

Biology Building-Shutdown and Lockout of the Building for Hot Water System Maintenance, May 6-7, 2017, 6:00am-6:00pm

Lambton Tower/Erie Hall-Hot Water System Flush, May 7, 2017, 6:00am-6:00pm

Dillon Hall-Hot Water System Flush, May 5, 2017, 6:00am-6:00pm

Essex Hall-Shutdown of Airhandling Unit (HV8), May 3, 2017, 10:00am-12:00pm

Pitt Ferry Building-Emergency Generator, May 26, 2017, 8:00am-11:00am

Dillon Hall/Chrysler Hall South-Flooring Repairs, May 5, 2017, 8:00am-5:00pm

Erie Hall-Replace Floor Tiles at Stairwell Landing and Room 5104, May 3, 2017, 8:00am-5:00pm

Jackman Dramatic Art Centre-Floor Repair in Room 110, May 3, 2017, 8:00am-5:00pm

Biology Building-Room 122, Electrical Work for AV Upgrades, May 2, 2017, 8:30am-4:00pm

Campus Thermo-graphic Drone Scanning of Building Walls and Rooftops, May 6-7, 2017

Biology Parking Lot-Construction of the River Commons, May 8-September 29, 2017, 7:00am-5:00pm

Chrysler Hall South-Temporary Closure of Northwest Building Exit, May 1-8, 2017, 8:00am-4:00pm

Laurier Hall-Fire Alarm Assessments, May 16-18, 2017, 9:00am-4:00pm

Alumni Hall-Fire Alarm Assessments, May 2-4, 2017, 9:00am-4:00pm

MacDonald Hall-Fire Alarm Assessments, May 9-11, 2017, 9:00am-4:00pm

April 2017

DATE REVISED: Assumption Church Parking Lot Closed-April 28, 2017, 8:00am-8:00pm

Leddy Library (Main and West) Building/Odette Building/Education Building/Law Building-Hot Water System Flush, April 29-30, 2017, 6:00am - 6:00pm

Chrysler Hall Tower/Chrysler Hall South/Chrysler Hall North-Hot Water System Back in Operations, April 26, 2017

UPDATED: CAW Student Centre-Fire Alarm Testing, April 24-26, 2017, 7:30am-4:00pm

Assumption Hall-Survey for Accessible Ramp Design, April 26, 2017, 7:00am-4:00pm

Chrysler Hall South-Installation of Lockers in CHS 181 and 1st Floor-Corridor, April 26-27, 2017, 8:00am-4:30pm

Education Building-Window Washing, April 25-27, 2017, 7:00am-4:00pm

Biology Building-Exhaust Fan Shutdown, April 25-27, 2017

Tunnel Water Testing-April 28-May 1, 2017, 6:00am-2:00pm

Assumption Hall-Minor Construction Work in Office 305 and 307, April 24-27, 2017, 9:00am-12:00pm

Chrysler Hall Tower/Chrysler Hall South/Chrysler Hall North-Hot Water System Flush, April 22-23, 2017, 6:00am - 6:00pm

Assumption Church Parking Lot Closed-April 30-May 1, 2017, 8:00am-5:00pm

CAW Student Centre-Installation of Sprinkler System and Fire Alarm System, April 24-26, 2017, 7:30pm-4:00pm

North of the Odette Building-Installation of Concrete Pad-April 24-May 1, 2017, 7:00am-5:00pm

Campus Wide - Switch from Heating Mode to Cooling Mode, May 1 to October 1, 2017

BUILDINGS REVISED: Facilities Condition Assessment with VFA, April 11 - 21, 2017, 7:00am-4:00pm

Laurier Hall-Flush Hot Water System, April 13-16, 2017, 4:00pm - 4:00pm

Essex Hall-Stage Area Renovations, April 24-30, 2017, 7:00am-5:00pm

Tunnel Isolation Valve Replacements, April 18, 2017, 6:00am-2:00pm

Essex Hall-Repairs on Pans AC12 and AC13, April 17-22, 2017, 6:00am-2:00pm

Domestic Hot Water Shutdown Until Further Notice

Chrysler Hall Tower-Emergency Hot Water Shutdown, April 12-13, 2017

Essex Hall-Gas Breach Investigation and Repair at Gas Meter-Wyandotte Street, April 11-28-2017, 6:00am-6:00pm

Tunnel Insulation Repair, April 12-30, 2017, 6:00am-2:00pm

Facilities Condition Assessment with VFA, April 11 - 21, 2017, 7:00am-4:00pm

Laurier Hall-Asbestos Abatement and Valve Removal, April 11, 2017, 6:00am-2:00pm

Biology Building-Flaking Paint Removal, April 12-13, 2017, 8:00am-5:00pm

Pitt Ferry Building-Monthly Inspections and Testing of Emergency Generator and Ligting, April 28, 2017, 8:00am-11:00am

DATE/TIME REVISED: Science and Research Innovation Facility (SRIF) Project – Electrical Shutdown, April 15, 2017

DATE/TIME REVISED: Science and Research Innovation Facility (SRIF) Project – Data Shutdown, April 15, 2017

Chrysler Hall Tower-5th Floor Xerox Relocation, April 17-21, 2017, 8:00am-5:00pm

Education Building-Installation of New Railing, April 12-20, 2017, 7:00am-5:00pm

Lambton Tower-Chilled Coil Repair, April 11-13, 2017, 6:00am-2:00pm

Essex Hall-Motorized Damper Replacement, April 11-20, 2017, 6:00am-2:00pm

University Computer Centre-Breaching Repair Call Centre, April 11-13, 2017, 6:00am-2:00pm

Pitt Ferry Building-April 10-11, 2017, Flow Valve Repair, 6:00am-2:00pm

Centre for English Language Development-Installation of Concrete Pad for Benches-April 3-17, 2017, 7:00am-4:00pm

Science and Research Innovation Facility (SRIF) Project – Data Shutdown, April 12-13, 2017, 11:00pm-5:00am

Science and Research Innovation Facility (SRIF) Project – Electrical Shutdown, April 12-13, 2017, 11:00pm-11:00am

Science and Research Innovation Facility (SRIF) Project – Steam Outage, April 8-9, 2017, 11:00pm-5:00am

Pitt Ferry Building-Emergency Generator, April 7, 2017, 7:00am-10:00am

Great Lakes Institute of Environmental Research (GLIER)-Conference Room Renovation, April 11-June 30, 2017, 8:00am-5:00pm

Biology Building-Roof Replacement, April 10-30, 2017, 7:00am-5:00pm

Vanier Hall/Cartier Hall- Vanier Circle Driveway - Field Verification, April 12, 2017, 8:00am-1:00pm

Former Clark Residence-Site Restoration, April 10-21, 2017

Essex Hall-Mould Abatement-Phase 2, Basement and 2nd Floor, April 17-28, 2017

CANCELLED UNTIL FURTHER NOTICE: Science and Research Innovation Facility (SRIF) Project – Steam Outage, April 5, 2017, 5:00am-6:00pm

Erie Hall-Washroom Upgrades Project - Air Balancing, April 3, 2017, 8:00am-2:00pm

St. Denis Fieldhouse-Drain Pan Repair, April 2-4, 2017, 6:00am-2:00pm

Science and Research Innovation Facility (SRIF) Project – Steam Outage, April 5, 2017, 5:00am-6:00pm

Essex Hall-Inspection and Maintenance on Fumehood Exhaust Fan, April 3, 2017, 7:30am-3:30pm

Science and Research Innovation Facility (SRIF) Project – Water Main Shutdown, April 3, 2017, 10:00am-8:00pm

Essex Hall-HVAC Shutdown: South Wing-Basement, 1st and 2nd Floors, April 19-28, 2017

Assumption Hall/Dillon Hall-Roof Tops Repairs and Inspections, April 3, 2017, 8:00am-4:30pm

Centre for English Language Development-Installation of Concrete Pad for Benches-April 3-7, 2017, 7:00am-4:00pm

Education Building-Building Walk-thru to Identify Fire Alarm Devices, April 18-20, 2017, 9:00am-4:00pm

Chrysler Hall North/Chrysler Hall South/Chrysler Hall Tower-Building Walk-thru to Identify Fire Alarm Devices, April 4-6, 2017, 9:00am-4:00pm

March 2017

Erie Hall/Lambton Tower-Washroom Exhaust Fan, 3rd Floor Ductwork and M101 Fire Alarm Detector, March 31, 2017, 7:30am-12:00pm

Human Kinetics-Installation of New Flooring in Fieldhouse, April 11-May 20, 2017, 8:00am-5:00pm

Psychology-Psychological Services and Research Centre Moving from 332 Sunset to 2629 Riverside Drive, April 18-21, 2017, 8:00am-5:00pm

Chrysler Hall North-File Cabinets Move to 2629 Riverside Dr., April 3-7, 2017, 8:00am-5:00pm 

Human Kinetics- Removing Storage Cages, April 3-4, 2017, 8:00am-5:00pm

Erie Hall-Ceiling Space Clean Up, March 25, 2017, 8:00am-6:00pm

Essex Hall/Jackman Dramatic Art Centre-Emergency Exits That Lead to SRIF Construction Site Closed, March 23 -April 28, 2017, 1:00pm-6:00pm

Centre for Engineering Innovation- MEMS Lab Fit-Out, March 27-September 8, 2017, 8:00am-7:00pm

Chrysler Hall Tower-Laminate Floor Repairs/Air Handling Units to Full Exhaust-March 24-25, 2017, 3:00pm-7:00pm

Law Building/Leddy Library West Wing/Leddy Library (East) Main Building-Repair of Plugged Sewer Line, March 23-29, 2017, 8:00am-4:30pm

Essex Hall - 335 Renovations/Fire Watch, March 24, 2017, 8:00am-12:00pm 

Science and Research Innovation Facility (SRIF)-Pre-Construction Investigation, March 24, 2017, 9:00am-5:00pm

Leddy Library West Wing-Door Upgrades Project with Type II Work Enclosures, February 28-April 8, 2017, 7:30am-7:30pm

Essex Hall-Mould Abatement/HVAC Shutdown, March 22, 2017, 4:30pm-10:30pm

Science and Research Innovation Facility (SRIF)-Curb Island Removal-March 22, 2017, 10:00am-4:00pm

Science and Research Innovation Facility(SRIF)/Essex Hall/Dramatic Arts-Gas Load Conditions Evaluations-March 17, 2017, 9:00am-1:00pm

Faculty of Education/Odette Building/Vanier Hall/Assumption Hall/Dillon Hall/Human Kinetics/St. Denis Field House/Energy Conversion Centre-Campus Roof Upgrades, March 20-April 24, 2017, 8:30am-4:30pm

Pitt Ferry Building-Building Envelope, March 27, 2017, 9:00am-1:00pm

Pitt Ferry Building-Plumbing Monthly Inspections, March 27, 2017, 9:00am-1:00pm

Pitt Ferry Building-Sprinkler System Inspections, March 29, 2017, 9:30am-11:30am

Pitt Ferry Building-Emergency Generator/Emergency Lighting Inspections, March 31, 2017, 8:00am-11:00am

Pitt Ferry Building-Fire Protection, March 31, 2017, 8:00am-10:00am

Science and Research Innovation Facility (SRIF)-Live Tap into Water Main North of SRIF Building, March 14-15, 2017, 8:00am-6:00pm

Essex Hall-Mould Abatement/HVAC Shutdown, March 9, 2017, 4:30pm-10:30pm

Vanier Hall/CAW Student Centre-Facilities Condition Assessment with VFA, March 15-16, 2017, 7:00am-4:00pm

Alumni Hall/Laurier Hall/MacDonald Hall/Cartier Hall-Facilities Condition Assessment with VFA, March 13-15, 2017, 7:00am-4:00pm

Science and Research Innovation Facility (SRIF)/Essex Hall-Relocation of Gas Line and Water Main to Re-Feed Essex Hall Building, March 20-April 15, 2017, 8:00am-6:00pm

Science and Research Innovation Facility (SRIF)-Live Tap into Water Main North of SRIF Building, March 13, 2017, 8:00am-6:00pm

Pitt Ferry Building-Installation of Tile Floor at New Door Locations, March 8, 2017, 8:00am-5:00pm

Human Kinetics/St. Denis Fieldhouse-Building Walk-thru to Identify Fire Alarm Devices, March 21-23, 2017, 9:00am-4:00pm

Erie Hall/Lambton Tower-Building Walk-thru to Identify Fire Alarm Devices, March 7-9, 2017, 9:00am-4:00pm

Essex Hall-335 Renovations/Fire Watch, March 9, 2017, 8:00am-10:00am

Leddy Library (East) Main Building/Leddy Library West Wing-Door Upgrades Project with Type II Work Enclosures, February 28-March 8, 2017, 7:30am-1:30pm

Chrysler Hall Tower/Chrysler Hall South/Chrysler Hall North/Erie Hall/Lambton Tower-Review of Existing Lights, March 14-23, 2017, 8:00am-8:00pm

Chrysler Hall Tower-Wall Repairs, March 2, 2017, 7:45am-4:30pm

Essex Hall- Water Leak Repair in Washroom, March 3, 2017, 12:00pm-4:00pm

Centre for Engineering and Innovation-Emergency Steam Outage, March 1, 2017, 6:00am-10:00am

Science and Research Innovation Facility (SRIF)/Essex Hall/Jackman Dramatic Art Centre/MacDonald Hall-Full Construction Site Hoarding, March 6, 2017-May 30, 2018, 8:00am-6:00pm

Essex Hall-Mould Abatement/HVAC Shutdown, March 7, 2017, 4:00pm-11:00pm

Essex Hall/Essex Hall-Chemical Control Centre-Shut Off of Natural Gas Service to Essex Hall North Side, March 2-3, 2017, 8:00am-4:00pm

February 2017

Chrysler Hall Tower/Medical Education Building, Maintenance in Mail Room Pipe Chase, February 28-March 8, 2017, 6:00am-4:00pm

Lambton Tower-Maintenance in Penthouse Mechanical Room, February 28-March 8, 2017, 6:00am-4:00pm

Leddy Library (East) Main Building/Leddy Library West Wing-Door Upgrades Project with Type II Work Enclosures, February 28-March 8, 2017, 7:30am-1:30pm

Pitt Ferry Building-Installation of Mechanical Access Platform at Rooftop Chiller, March 2-3, 2017, 8:00am - 5:00pm

Essex Hall-Mould Abatement, March 6-May 30, 2017, 8:00am-5:00pm

CAW Student Centre-Fire Alarm System Updates, February 28, 2017, 8:00am-4:00pm

University Computer Centre-Testing of the Fire Suppression System, March 1, 2017, 8:00am-4:00pm

Chrysler Hall Tower/Essex Hall-Chemical Control Centre-Testing the Fire Suppression System, February 28, 2017, 8:00am-4:00pm

Leddy Library (East) Main Building/Leddy Library West Wing-Door Upgrades Project with Type II Work Enclosures, February 28-March 8, 2017, 7:30am-1:30pm

Centre for Engineering Innovation-Security Camera and Emergency Phones Installation, February 27-March 3, 2017, 8:00am-5:00pm

Essex Hall-Room 335 Renovations/Asbestos Abatement, February 22, 2017, 8:30am-4:30pm

Grounds Building-Replacement of Door Frame and Door at Garage, February 22, 2017, 7:30am-4:30pm

Chrysler Hall North/Lambton Tower-Elevator in Service Mode, February 21-22, 2017, 9:00am-4:00pm

CAW Student Centre-Fire Alarm Shutdown for New Sprinkler Installation, February 21, 2017, 7:30am-4:00pm

Canterbury Parking Lot, 197 Sunset Avenue-Installation of Exterior Lights, February 23, 2017, 8:00am-5:00pm

Chrysler Hall North-Elevator in Service Mode, February 21-22, 2017, 9:00am-4:00pm

Medical Education Building-Rework Ductwork and Lighting Panel, February 17-March 10, 2017, 7:00am-5:00pm

CAW Student Centre-Domestic Hot Water Shutdown, February 21-22, 2017, 5:30pm-4:30pm

Erie Hall/Lambton Tower-Washroom Exhaust Fan and HVAC, February 15-March 10, 2017, 7:30am-4:30pm

Chrysler Hall Tower-Installation of Guard Rail on Roof Top, February 14, 2017, 8:00am-4:00pm

Essex Hall-Room 335 Renovations, February 15-March 31, 2017, 7:00am-5:00pm

Essex Hall-Room 335 Renovations/Asbestos Abatement, February 15, 2017, 4:30pm-10:30pm

Science and Research Innovation Facility (SRIF)-Hoarding for the Early Works, February 15, 2017, 10:00am-5:00pm

Emergency Phone Pole Installation-February 13-28, 2017, 7:00am-5:00pm

Pitt Ferry Building-Plumbing Monthly Inspections, February 22, 2017, 12:00pm-4:00pm

Pitt Ferry Building-Building Envelope, February 22, 2017, 12:00pm-4:00pm

Pitt Ferry Building-Emergency Generator/Emergency Lighting Inspections, February 23, 2017, 9:00am-12:00pm

Pitt Ferry Building-Fire Protection, February 24, 2017, 8:00am-10:00am

Pitt Ferry Building-Sprinkler System Inspections, February 28, 2017, 8:00am-10:00am

Great Lakes Institute of Environmental Research-Flooring Replacement, February 11, 2017, 8:00am-5:00pm

Essex Hall-Air Handling Upgrades, February 8, 2017, 4:00pm-9:00pm

Chrysler Hall North-Electrical Work(Power,Data,Phone), February 8-10, 2017, 8:00am-4:30pm

Music Building/Medical Education Building-Heating and Cooling/Ventilation, February 13-17, 2017, 6:00am-4:00pm

Leddy Library (East) Main Building/Leddy Library West Wing-Heating and Cooling/Ventilation, February 6-10, 2017, 6:00am-4:00pm

Chrysler Hall Tower-Laminate Flooring Repair/Air Handling Units to Full Exhaust, February 17-20, 2017, 3:00pm-7:00am

Essex Hall, Jackman Dramatic Art Centre, University Computer Centre, Science Research and Innovation Centre - Mobilization for Fence/Hoarding at New Project Site - Feb 6, 2017, 7:00 am to 6:00 pm

CAW Student Centre/Assumption Hall - Parking Lot Access Partially Restricted, February 3, 2017, 8:00am-4:00pm

Tunnel-Removal of Weak Concrete Spots, February 3-10, 2017, 8:00am-4:00pm

Chrysler Hall Tower-Installation of New Carpeting, February 1, 2017, 4:30pm-11:00pm

Chrysler Hall North-Bearing Replacement, February 4, 2017, 6:00am-6:00pm

Biology Building-Coil Installation, February 3-4, 2017, 12:00pm-4:00pm

Assumption Hall-Asbestos Reassessment, February 1, 2017, 1:00pm-2:30pm

January 2017

Essex Hall/Erie Hall-Banner Removal and Installation, January 30, 2017, 8:00am-5:00pm

Fire Alarm Test Schedule 2017

Pitt Ferry Building-Warranty Repairs, January 27, 2017, 8:00am-4:00pm

Dillon Hall-Guarding Installation on HVAC Units, January 26-31, 2017, 8:00am-4:00pm

CAW Student Centre-Fire Alarm System Out of Service, January 25, 2017, 9:30am-11:00am

Chrysler Hall Tower-1st Floor HVAC Shutdown, January 19, 2017 (12:00pm-5:30pm), January 20, 2017 (8:00am-12:00pm)

CAW Student Centre-Shutdown of Electrical Panel LP-N, January 20, 2017, 7:00am-4:00pm

Pitt Ferry Building-Installation of New Hasp Lock on Courtyard Gate, January 16, 2017, 8:00am-5:00pm

Leddy Library (East) Main Building-Water Cooler/Bottle Filling Station Installation, January 19-20, 2017, 8:00am-5:00pm

Health Education Centre-Interior Sign Upgrades, January 16-20, 2017, 8:30am-4:30pm

Pitt Ferry Building-Plumbing Inspections, January 19, 2017, 12:00pm-4:00pm

Pitt Ferry Building-Building Envelope, January 19, 2017, 12:00pm-4:00pm

Pitt Ferry Building-Sprinkler System Inspections, January 25, 2017, 8:00am-10:30am

Pitt Ferry Building-Emergency Generator Inspection, January 27, 2017, 8:00am-12:00pm

Pitt Ferry Building-Fire Protection Inspections, January 27, 2017, 10:30am-12:00pm

Essex Hall-Main Entrance Lobby Painting, January 23-January 28, 2017, 8:00am-5:00pm

Laurier Hall/Vanier Hall-Emergency Repair on Perimeter Heating Line, January 17, 2017, 4:00am-2:00pm

Assumption Hall-Contractors Site Visit and Tour, January 13, 2017, 10:00am-11:00am

Essex Hall-Emergency Excavation To Repair Sewer Line, January 11, 2017, 8:00am-4:00pm

Freed Orman Centre-Washrooms Hot Water Shutdown, January 12, 2017-February 1, 2017, 8:00am-5:00pm

Biology Building-Emergency Repair on Mixing Boxes, January 10, 2017, 6:00am-2:00pm

Essex Hall-Signage Removal, January 11, 2017, 9:00am-4:00pm

Essex Hall/Jackman Dramatic Art Centre/University Computer Centre-Borehole Drilling for Soil Testing, January 10-12, 2017, 7:00am-6:00pm

Biology Building-Fire Alarm System Testing, January 9, 2017, 7:00am-5:00pm

Human Kinetics-Insulating and Sealing Outside Walls, January 9-13, 2017, 7:00am-5:00pm

Assumption Hall-Contractors Site Visit and Tour, January 6, 2017, 10:00am-11:00am

CAW Student Centre-Fire Alarm System Shutdown, January 4, 2017, 8:00am-1:00pm

Essex Hall/Jackman Dramatic Art Centre/University Computer Centre-Borehole Drilling for Soil Testing, January 6-7, 2017, 7:00am-6:00pm

Law Building/Education Building/Leddy Library (East) Main Building/Leddy Library West Wing/Lambton Tower-Door Upgrades, January 3-March 10, 2017, 7:30am-4:30pm

Law Building/Health Education Centre-Sign Upgrades, January 3-13, 2017, 8:30am-4:30pm

December 2016

Odette School of Business-Cleaning and Painting, December 23, 2016 - January 2, 2017, 8:00am-4:00pm

Health Education Centre/Essex Hall-Painting, December 23, 2016-January 2, 2017, 8:00am-4:00pm

CAW Student Centre-Fire Alarm Shutdown, December 28-29, 2016, 8:00am-4:00pm

Health Education Centre-Painting Room 102 and 103, December 23, 2016 to January 2, 2017, 8:00am-6:00pm

Lambton Tower-Ceiling Tile Replacement, December 21, 2016, 5:00pm-10:00pm

Centre for Engineering Innovation-Fire Alarm Testing, December 23, 2016, 7:00am-4:00pm 

University Computer Centre-Exterior Surfaces Ducts Cleaning, December 17, 2016, 6:00am-4:00pm

Biology Building-Fume Hood Exhaust Fan Shutdown, December 19, 2016, 7:00am-5:00pm

Assumption/CAW Student Centre Tunnel-Mold Remediation, January 9-February 1, 2017, 8:00am-5:00pm

Pitt Ferry Building-Exit Sign Installations, December 13, 2016, 8:00am-5:00pm

Pitt Ferry Building-Emergency Generator Monthly Inspections and Testing, December 15, 2016, 8:00am-12:00pm

Pitt Ferry Building-Building Envelope Inspection, December 22, 2016, 12:00pm-4:00pm

Pitt Ferry Building-Plumbing and Roof Inspections, December 22, 2016, 12:00pm-4:00pm

Pitt Ferry Building-Sprinkler System Inspection, December 23, 2016, 8:00am-10:30am

Pitt Ferry Building-Fire Protection Monthly Inspections and Testing, December 23, 2016, 10:30am-12:00pm

Alumni Hall-Power Outage for High Voltage Testing, December 22, 2016, 9:00am-1:00pm

Chrysler Hall North-Painting Offices/Sanding Wood Doors, December 12-30, 2016, 8:00am-12:00pm 

Biology Building-Fume Hood Exhaust Fan Shutdown, December 14, 2016, 7:00am-5:00pm

Pitt Ferry Building-Emergency Door Toppers Repair, December 11, 2016, 6:00am-2:00pm

CAW Student Centre-Emergency Steam Line Repair, December 10, 2016, 4:00am-8:00am

Biology Building-Emergency Mixing Box Repair, December 10, 2016, 6:00am-2:00pm

Biology Building-Fire Alarm Outage/Commissioning System on 2nd Floor, December 15, 2016, 7:00am-4:00pm

Pitt Ferry Building-Installation of Roller Latches on Doors, December 19-20, 2016, 8:00am-5:00pm

Pitt Ferry Building-Painting, December 9, 2016, 8:00am-5:00pm

CAW Student Centre-Emergency Steam Line Repair, December 10, 2016, 6:00am-2:00pm

Essex Hall-Electrical Work/Ceiling Repair/Painting, December 13, 2016-January 9, 2017, 8:00am-4:00pm

Centre for Engineering and Innovation-Minor Welding Task, December 7, 2016-January 9, 2017, 7:00am-4:00pm

Pitt Ferry Building-Metal Gates Installation, December 8, 2016, 8:00am-5:00pm

CAW Student Centre-Fire Alarm Shutdown, December 12, 2016, 8:00am-4:00pm

MacDonald Hall-Fire Pump Out of Service, December 8, 2016, 8:00am-4:00pm

Union House-Roof Repair and Upstairs Room Repair, December 8-9, 2016, 8:00am-4:00pm

Centre for Engineering Innovation-Test and Verification of Smoke Evacuation System, December 5, 2016-January 29, 2017, 7:00am-4:00pm

Great Lakes Institute of Environmental Research-Valve Connection on Cold Water Line, December 5, 2016, 8:00am-4:00pm

Lambton Tower-Emergency Steam Repair, December 3, 2016, 6:00am-2:00pm

Essex Hall-Emergency Steam Repair, December 3, 2016, 6:00am-2:00pm

November 2016

CAW Student Centre-Saw-cutting of First Floor, December 5-6, 2016, 7:30am-2:00pm

Energy Conversion Centre-Boom Truck Set Up on West Side of ECC, November 29, 2016, 8:00am-4:00pm

Joyce Entrepreneurship Centre-Southside Concrete Sidewalk Installation, December 5-9, 2016, 8:30am-4:30pm

Pitt Ferry Building-Installation of Exit Doors and Exit Signs, November 22-December 2, 2016, 8:00am-5:00pm

Essex Hall-New Epoxy Flooring, November 23-27, 2016, 8:30am-4:30pm

Essex Hall-Emergency Steam Repair, November 22, 2016, 7:00am-2:00pm

Human Kinetics-Winterizing Coils, November 21, 2016, 7:00am-2:00pm

CAW Student Centre-Demolition and Construction Work on the New Student Lounge, November 22, 2016-March 31, 2017, 7:00am-3:00pm

Essex Hall-Domestic Hot and Cold Water Shutdown, November 22, 2016, 7:30am-12:00pm

Education Building/Centre for Automotive Research & Education/Centre for English Language Development-Natural Gas Meter Replacement, November 23, 2016, 8:30am-4:00pm

Essex Hall-Emergency Steam Repair, November 21, 2016, 7:00am-2:00pm

Law Building-Wireless Coverage Testing, November 15, 2016, 12:00pm-3:00pm

Pitt Ferry Building-Exterior Lights Inspection, November 22, 2016, 5:30pm-8:00pm

Student Quad-Relocation of Trees, November 18-20, 2016, 7:00am-4:00pm

Forge Fitness-Wireless Coverage Testing, November 15, 2016, 8:30am-2:00pm

Essex Hall-Inspection and Maintenance on Fumehood Exhaust Fan, November 22, 2016, 7:00am-12:00pm

Essex Hall-Reconstruct Vent Piping on Vacuum Pump in Basement, November 15, 2016, 7:00am-1:00pm

Pitt Ferry Building-Emergency Generator, November 25, 2016, 8:00am-12:00pm

Pitt Ferry Building-Fire Protection Inspections and Testing, November 25, 2016, 10:30am-12:00pm

Pitt Ferry Building-Inspection of the Sprinkler System, November 28, 2016, 1:00pm-3:00pm

Pitt Ferry Building-Building Envelope Inspections, November 29, 2016, 12:00pm-4:00pm

Pitt Ferry Building-Plumbing Inspection, November 29, 2016, 12:00pm-4:00pm

Essex Hall-Electricial/Plumbing, November 15-18, 2016, 8:00am-4:30pm

Chrysler Hall Tower-Renovations to Accounts Payable Kiosk, November 14-18, 2016, 7:00am-4:00pm

Essex Hall-Natural Gas Outage, November 11-15, 2016, 8:00am-4:00pm

Chrysler Hall Tower West Elevator is Out of Service - November 8, 2016, 8:00am-11:00pm 

Chrysler Hall Tower-6th Floor, Room 616 & Corridor HVAC Unit to be Isolated, November 8, 2016, 7:30am-12:00pm

Pitt Ferry Building-Exterior Lights Inspection, November 23, 2016, 5:30pm-8:00pm

Dillon Hall-Elevator Shut Down, November 2-7, 2016, 12:00pm-4:00pm

Chrysler Hall Tower - HVAC, November 1, 2016, 7:30 am - 4:30 pm

Biology Building-Steam/Domestic Hot Water/Heating-November 1, 2016, 7:00 am - 1:00 pm

Pitt Ferry Building-Installation of New Threshold and Aluminum Sill, November 3-4, 2016, 8:00am-5:00pm

Pitt Ferry Building-Installation of Roller Latches on Door Frames, November 2, 2016, 8:00am-5:00pm

Joyce Entrepreneurship Centre-Installation of Partition Wall, November 2, 2016, 8:30am-4:30pm

October 2016

Clark Residence I & II-Demolition, October 31, 2016 - November 30, 2016, 8:00 am - 5:00 pm

Pitt Ferry Building-Installation of Additional Suite Exit Doors and Exit Signs, October 31- November 4, 2016, 8:00am-5:00pm

Chrysler Hall Tower -West Elevator Out of Service Due to Departmental Move, October 28-31, 2016, 9:00am-4:00pm

DATE EXTENSION: Biology Building-Relocation of the FDC Connection, October 17-28, 2016, 7:00am-5:00pm

DATE EXTENSION: Biology Building-Relocation of the FDC Connection, October 17-25, 2016, 7:00am-5:00pm

Laurier Hall-Replace Caulking on South Side of Building, October 21, 2016, 8:00am-5:00pm

Pitt Ferry Building-Plumbing Inspections, October 27, 2016, 8:00am-12:00pm

Pitt Ferry Building-Building Envelope Inspection, October 27, 2016, 8:00am-12:00pm

Pitt Ferry Building-Room Divider Maintenance, November 2, 2016, 2:30pm-5:30pm

Alumni Hall-Building Envelope Testing, October 20, 2016, 5:00am-12:00pm

Chrysler Hall Tower-Painting Door Frames, October 18, 2016, 7:30am-12:00pm

Pitt Ferry Building-Emergency Generator Monthly Inspection, October 21, 2016, 8:00am-12:00pm

Pitt Ferry Building-Sprinkler System Monthly Inspection, October 21, 2016, 8:00am-10:00am

Pitt Ferry Building-Fire Protection Monthly Inspection, October 28, 2016, 10:30am-12:00pm

Essex Hall-Grass Area of Courtyard Closure, October 19-21, 2016, 8:00am-5:00pm

Pitt Ferry Building-Divider Maintenance, October 21, 2016, 9:00am-11:00am

Clark Residence-Phase 1-Watermain Work, October 14, 2016, 7:00am-4:30pm

Assumption Hall-Temporary Closure of West Building Entrance (Huron Church), October 19, 2016, 9:00am-4:00pm

Essex Hall-South End Freight Elevator Out-of-Service Until Further Notice, October 11, 2016, 7:00am-10:00pm

Biology Building-Relocation of the FDC Connection, October 17-21, 2016, 7:00am-5:00pm

Pitt Ferry Building, Panel Ceiling Installations, October 12-13, 2016, 8:00am-5:00pm

Flushing and CCTV Inspection of Sewer Lines-October 17-19, 2016, 8:00am-4:00pm

DATE REVISED: Law Building-Sound Proof Counsellor Room, October 7-14, 2016, 8:00am-5:00pm

Dillon Hall-Installation of Carpeting in the South Section of Dillon Hall Basement, October 31-November 4, 2016, 5:00pm-11:00pm

Dillon Hall-Installation of Carpeting in the North Section of Dillon Hall Basement, October 24-28, 2016, 8:00am-4:00pm

Law Building-Sound Proof Counsellor Room, October 11-14, 2016, 8:00am-4:00pm

Great Lakes Institute of Environmental Research-Brick Repair on Exterior Wall, October 11-14, 2016, 8:00am-4:00pm

Chrysler Hall Tower (CHT)-HVAC, 2nd Floor Washrooms, October 5 - 6, 2016, 8:00 am - 3:00 pm

Medical Education Building (MEB)-Inspection of Fire Dampers, October 5, 2016, 7:00 am - 1:00 pm

Chrysler Hall Tower (CHT)-HVAC 6th Floor, Rm 616 and Corridor, October 4, 2016, 7:30 am - 1:00 pm

Chrysler Hall North-G120 Noise Due to Drilling or Hammer Use, October 3-7, 2016, 8:00am-4:00pm

Erie Hall/Lambton Tower-2015 Washroom Upgrades Project: Fire Alarm Installation and Verification, October 4, 2016, 7:30am-1:30pm

Great Lakes Institute of Environmental Research-Room 110 Renovations, October 5-December 30, 2016, 7:00am-6:00pm

846 Sunset Garage-Electrical Connection Updates, October 6-7, 2016, 7:00am-5:00pm

Pitt Ferry Building-Scheduled Fire Drill, October 5, 2016, 3:30pm-4:00pm

September 2016

Chrysler Hall Tower-Install New Door Opening, Type II Asbestos Procedure, September 30, 2016, 7:00am-9:00am

Assumption Hall-Site Conditions Inspection, September 29, 2016, 1:00pm-4:00pm

Pitt Ferry Building - Sprinkler System, September 30, 2016, 8:00 am - 12:00 pm

Pitt Ferry Building - Fire Protection, September 30, 2016, 10:30 am - 12:00 pm

Pitt Ferry Building-Drywall Repair, September 28, 2016, 8:00am-4:00pm

Education Building-Repair Concrete Walkway to Parking Lot Q Wheelchair Access Restricted, September 27-October 4, 2016, 8:00am-4:00pm

Alumni Hall-Conduction of Infrared scans, September 26, 2016 at 7:00 am until September 30, 2016 at 3:00 pm

Medical Education Building - Steam - September 27-28, 2016, 7:00 am - 4:00 pm

University Computer Centre - Ventilation, September 26 - October 2, 2016, 7:00 am - 4:00 pm

Pitt Ferry Building - Building Envelope, September 29, 2016, 8:00 am - 12:00 pm

Pitt Ferry Building - Plumbing, September 29, 2016, 8:00 am - 12:00 pm

Campus Wide - Heating and Cooling, October 3 - 17, 2016, 12:00 pm - 10:00 am

Essex Hall-External Cleaning of Duct Work, September 26-27, 2016, 7:30 am - 4:00 pm

GLIER-Access to Hallway at First Floor, September 28 - 30, 2016, 7:00 am - 12:00 pm

Clark Residence I & II-Occasional Parking Lot Closures, September 26, 2016 - October 14, 2016, 8:00 am - 5:00 pm

Assumption Hall/Essex Hall-Heating and Ventilation, September 14 - 30, 2016, 7:00 am - 4:00 pm

Centre for Engineering Innovation (CEI)-Main Entrance Partially Blocked-September 21, 2016, 5:00 pm - 9:00 pm

Medical Education Building-Temporary Parking Closure in Lot W, September 21-27, 2016, 7:00am-5:00pm

Pitt Ferry Building-Milling and Paving of Road along Pitt St. and Ferry St., September 21, 2016, 8:00am-5:00pm

Joyce Entrepreneurship Centre-Fire Alarm/Sprinkler System Updates, September 22, 2016, 7:30am-4:30pm

Chrylser Hall Tower, 6th Floor, Rm 600-Type 2 Asbestos-September 20, 2016, 8:30 am - 12:00 pm

Clark Residence I - Parking Lot Closed at Sunset Entrance, September 22, 2016 - November 25, 2016

Chrysler Hall Tower (CHT)-HVAC, 2nd Floor-September 19, 2016 @ 12:00 noon - September 21, 2016 @ 3:00 pm

LeBel Building, No Access to Rooms 101, 101-A, 101-B, September 15 - 16, 2016, 8:00 am - 5:00 pm

Leddy Library (East) Main Building-First Floor WiFi and N/E Lounge 1101 Upgrades, September 19- October 28, 2016, 8:00am-4:30pm

Leddy Library (East) Main Building-Type II Asbestos Abatement, September 15-16, 2016, 10:00pm-8:00am

Essex Hall-Mold Removal Treatment on Ductwork, September 14-16, 2016,  4:30pm-10:30pm

Pitt Ferry Building-Road Closures/Construction of Interior Areas, September 13-November 15, 2016, 8:00am-5:00pm

Assumption Hall/Essex Hall-Intermittent Fan Interruptions, September 14-19, 2016, 7:00am-4:00pm

Biology Building-HVAC Shutdown, September 13-15, 2016, 7:30am-4:00pm

Sprinkler Shutdown and Roof Access to Buildings for Installation of Banners, September 8-23, 2016, 8:00am-5:00pm

Assumption Hall/University Computer Centre-Parking Lot Access, September 2-4, 2016, 8:00am-4:00pm

Laurier Hall-Intermittent Fan Interruptions, September 2, 2016, 7:00am-4:00pm

Pitt Ferry Building-Power Outage, September 11, 2016, 7:30am-4:00pm

Joyce Entrepreneurship Centre-HVAC Shutdown, September 2, 2016, 7:30am-4:00pm

Pitt Ferry Building-Sprinkler System Inspection, September 8, 2016, 8:00am-12:00pm

Chrysler Hall Tower-Construction Work on 2nd Floor, September 6-10, 2016, 8:00am-4:00pm

Pitt Ferry Building-Building Envelope, September 1, 2016, 8:00am-4:00pm

August 2016

Essex Hall/Essex Hall(Chemical Control Centre)-Intermittent Fan Interruptions, August 29-September 29, 2016, 7:00am-4:00pm

Odette School of Business-Doorway Out of Service-East Entrance, August 31 - September 6, 2016, 8:30am-10:00pm

Biology Building-Ceiling Tile Repair Work, August 31, 2016, 7:30am-4:00pm

Law Building/Leddy Library/Biology Building/Essex Hall-Emergency Steam Repair, August 27, 2016, 6:00am-10:00am

Welcome Centre-Fire Alarm System Testing and Verification, August 26, 2016, 7:00am-8:00am

Medical Education Building-HVAC Units Upgrade, August 24, 2016, 7:30am-1:30pm

Centre for Engineering Innovation-Lighting Upgrades, August 22-25, 2016, 7:30am-4:00pm

Human Kinetics-Air Conditioning-August 22-23, 2016, 7:00am-12:00pm

Cartier Hall - Minor Obstruction on East Side Drive in Vanier Circle, August 22 - 31, 2016, 8:00 - 4:00 pm

Centre for Engineering Innovation-Lighting Upgrades, August 22-25, 2016, 7:30am-4:00pm

Essex Hall-Wiring Installations, August 22-September 17, 2016, 7:00am-4:00pm

Pitt Ferry Building-Building Envelope Inspection, August 25, 2016, 8:00am-12:00pm

Pitt Ferry Building-Fire Protection Inspections, August 26, 2016, 10:30am-12:00pm

Pitt Ferry Building-Emergency Generator Inspections, August 26, 2016, 8:00am-12:00pm

Pitt Ferry Building-Sprinkler System Inspection, August 31, 2016, 8:00am-12:00pm

Lambton Tower/Centre for Automotive Research and Education-Annual Fire Alarm Operations and Verifications, August 31-September 1, 2016, 7:00am-4:00pm

Joyce Entrepreneurship Centre-Sprinkler System Upgrades, August 23, 2016, 7:30am-4:30pm

Medical Education Building-Repair Fire Dampers, August 18, 2016, 7:00am-1:00pm

Assumption Hall-Elevator Repairs, August 17-23, 2016, 8:00am-4:00pm

Law Building-Plumbing and Floor Repairs to Washrooms, August 19-26, 2016, 8:00am-5:00pm

Erie Hall - Fire Alarm System, August 18, 2016, 7:30 am - 4:00 pm

Essex Hall/UCC/Jackman Dramatic Art Centre/MacDonald Hall-Topographic Surveys-August 15-19, 2016, 8:00am-6:00pm

Annual Fire Alarm Operations and Verification, August 22-29, 2016, 7:00am-4:00pm

Annual Fire Alarm Operations and Verification, August 15-19, 2016, 7:00am-4:00pm

Vanier Hall-Repairs at Entrance Vestibule, August 12-17, 2016, 7:00am-4:00pm

Maintenance Building/Leddy Library West Wing/Education Building - Access to Some Parking Spaces, August 12-18, 2016, 6:30am-5:00pm

Essex Hall-Washing Plumbing Repair, August 12-14, 2016, 4:00pm-5:00pm 

Chrysler Hall North-Washroom Plumbing Repair, August 12-14, 2016, 4:00pm-5:00pm

Maintenance Building-Floor Repair, August 11-18, 2016, 8:00am-4:00pm

Cartier Hall- Air Conditioning Maintenance, August 22-26, 2016, 7:00am-12:00pm

Memorial Hall-Air Conditioning Maintenance, August 11-19, 2016, 7:00am-12:00pm

Power Generator Testing and Inspection, August 16-19, 2016, 8:00am-4:00pm

Sunset Avenue-Replacement of Concrete Panel, August 12, 2016, 7:00am-5:00pm

University Computer Centre (UCC)-Security Camera Installation, August 16 - 17, 2016, 7:00 am - 5:00 pm

Great Lakes Institute of Environmental Research (GLIER)-Air Conditioning, August 3 - 8, 2016, 7:00 am - 12:00 pm

UCC, Jackman Dramatic Art Centre, Essex Hall-Access to Grassed Areas, August 9 - 11, 2016, 8:00 am - 5:00 pm

Campus Wide Steam Outage for 15 Minutes-Steam and Hot Water, August 4, 2016, 1:00 pm - 2:00 pm

Essex Hall, Jackman Dramatic Art Centre, UCC-Access to Grassed Areas, August 4, 2016, 9:00 am - 5:00 pm

Annual Fire Alarm Operations and Verifications, August 8-12, 2016, 7:00am-4:00pm

Annual Fire Alarm Operations and Verifications, August 2-5, 2016, 7:00am-4:00pm

July 2016

Inspection for Facilities Survey Designated Substances, July 27 - November 8, 2016, 8:00am - 12:00am

Great Lakes Institute of Environmental Research-Mold Removal and Access Door Installation, July 29-August 5, 2016, 8:00am-4:00pm

Medical Education Building-Work in Service Shaft Adding Fire Dampers, July 27-August 26, 2016, 7:30am-4:30pm

Centre for English Language Development/Centre for Automotive Research and Education-Gas Meter Replacement, July 26, 2016, 12:00pm-4:00pm

Pitt Ferry Building-Building Envelope Inspection, July 28, 2016, 12:00pm-4:00pm

Street Parking/Sidewalk Along Huron Church Road-Construction of New Drop Off Circle-July 26-September 26, 2016, 7:00am-5:00pm

Biology Building-Repair Capped HVAC and Fumehood Exhaust Ductwork, July 20-21, 2016, 2:30pm-7:00am

Medical Education Building-Temporary Closure of California Avenue Entrance to Parking Lot W, July 25-August 12, 2016, 7:00am-5:00pm

Pitt Ferry Building-Dry Wall Repairs, July 20-26, 2016, 8:00am-12:00pm

Pitt Ferry Building-Air Conditioning/Ventilation, July 22-23, 2016, 7:00am - 4:00pm

Pitt Ferry Building-Sprinkler System Inspection, July 26, 2016, 8:00am - 12:00pm

Pitt Ferry Building-Emergency Generator Inspection and Testing, July 29, 2016, 8:00am - 12:00pm

Pitt Ferry Building-Building Envelope, July 29, 2016, 12:00pm - 4:00pm

Pitt Ferry Building-Fire Protection Inspection, July 29, 2016, 8:30am - 12:00pm

Pitt Ferry Building-Plumbing Inspections, July 29, 2016, 12:00pm - 4:00pm

Essex Hall-General Demolition Work for Rooms 115,118 and Suite 119 (Excluding Room 119A), July 20-August 19, 2016, 7:30am-4:30pm

Leddy Library East Main Building-Paint Room 105, July 18, 2016, 8:00am-4:30pm

MacDonald Hall-Cold and Hot Water Interruption, July 18, 2016, 8:00am-4:00pm

Biology Building-Repair Capped HVAC and Fumehood Exhaust Ductwork, July 20, 2016, 4:30pm-10:00pm

Chrysler Hall South-Room 181 Repair Work, July 14-29, 2016, 8:00am-4:30pm

Chrysler Hall Tower-Fire Suppression System Annual Inspection and Testing, July 25, 2016, 8:30am-10:30am 

Joyce Entrepreneurship Centre-Access to Main Lobby/Access to WFCU West Entrance, July 14-September 30, 2016, 8:30am-4:30pm

Medical Education Building/GLIER/Odette School of Business/Dillon Hall-Fire Alarm Operations and Verifications, July 25-29, 2016, 7:00am-4:00pm

DATE EXTENDED: Memorial Hall-Fire Alarm System Inspection, July 14, 2016, 9:00am-2:00pm

Laurier Hall/Alumni Hall/Centre for Engineering Innovation/Education Building/Centre for Automotive Research and Education (CARE) - Fire Alarm System Operations and Verifications, July 18-22, 2016, 7:00am-4:00pm

Campus Wide Steam Outage, July 9, 2016, 6:00 am - 2:00 pm

Biology Building-Heating and Cooling Yearly Maintenance, July 4-11, 2016, 7:00am-4:00pm

Pitt Ferry Building-Emergency Generator Testing, July 14, 2016, 8:00am-12:00pm

Memorial Hall-Fire Alarm System Inspection, July 13, 2016, 9:00am-2:00pm

Great Lakes Institute of Environmental Research-Fire Alarm System Inspection, July 6, 2016, 9:00am-2:00pm

Assumption Hall-New Flooring Installation, July 6-15, 2016, 8:30am-4:30pm

Essex Hall/Jackman Dramatic Art Centre/Human Kinetics/Leddy Library (East) Main Building-Annual Fire Alarm Operations and Verifications, July 4-8, 2016, 7:00am-4:00pm

MacDonald Hall/Welcome Centre/Innovation Centre/Odette School of Business-Annual Fire Alarm Operations and Verification, July 11-15, 2016, 7:00am-4:00pm

June 2016

Emergency Power Generator Annual Testing and Inspection, June 16-August 15, 2016, 8:00am-4:00pm

Energy Conversion Centre-Asbestos Abatement, June 25, 2016, 7:30am - 4:30pm

Chrysler Hall Tower-Emergency Fan Repair, June 14-17, 2016, 12:00pm-4:30pm

Demolitions of 2475 & 310 University Avenue West, 846 Sunset Avenue, June 20 - July 8, 2016, 7:00am-5:00pm

Laurier Hall - HVAC Maintenance, June 20-July 8, 2016, 6:00am-4:00pm

Biology Building - Fire Alarm Shut Down, June 14, 2016, 7:30am-5:00pm

Leddy Library (East) Main Building-Investigations of Air Flow in Various Washrooms, June 13, 2016, 8:30 am - 4:00 pm

DATE EXTENDED: Jackman Dramatic Art Centre- Replace Steam and Condensate Piping, June 10, 2016, 8:30am-4:00pm

REVISED AND EXTENDED: Erie Hall/Lambton Tower-Washroom Upgrades Project - Type II Asbestos Abatement, June 7-9, 2016, 8:00am-11:00pm

Lambton Tower-Asbestos Insulation Removal with Glove Bag, June 14, 2016, 7:15am-9:15am

Energy Conversion Centre/Essex Hall/Centre for English Development/Essex Hall-Chemical Control Centre-Annual Fire Alarm Operations and Verifications, June 27-30, 2016, 7:00am-4:00pm

St. Denis Fieldhouse-New Drip Plan Installation for Air Handler #2, June 9-10, 2016, 7:00am-4:00pm

LeBel Building/Alumni Hall/University Computer Centre-Fire Alarm Operations and Verifications, June 21-23, 2016, 7:00am-4:00pm

Jackman Dramatic Art Centre- Replace Steam and Condensate Piping, June 9, 2016, 7:00am-4:00pm

Annual Fire Alarm Operations and Verifications, June 13-17, 2016, 7:00am - 4:00pm

University Computer Centre/Energy Conversion Centre-Semi Annual Inspection and Testing, June 8, 2016, 8:00am-4:00pm

Leddy Library (West Wing & East Main Building), Essex Hall (Chemical Control Centre)-Semi Annual Inspection and Testing, June 7, 2016, 8:00am-4:00pm

Assumption Hall-Front Access to Assumption Hall Closed, June 6-13, 2016, 7:30am-7:00pm

Energy Conversion Centre/Centre for English Language Development/Maintenance Building-Domestic Cold Water Shutdown, June 4, 2016, 8:00am-2:00pm

Erie Hall/Lambton Tower- Washroom Upgrades Project Type II Asbestos Abatement, June 7-8, 2016, 8:00am-11:00pm

Alumni Hall-Heating/Cooling Maintenance and Inspection, June 6-13, 2016, 8:00am-4:00pm

Parking Lot W Closed for Construction Permanently-June 10, 2016, 12:00pm

Biology-Rough-In of Piping for Fumehoods Installation, June 1-14, 2016, 9:00am-5:00pm

Pitt Ferry Building-Elevator Inspections, June 1, 2016, 1:30pm-2:30pm

Pitt Ferry Building-Building Envelope, June 1, 2016, 8:00am-4:00pm

Pitt Ferry Building-Plumbing, June 1, 2016, 8:00am-4:00pm

Psychology Centre/Community Legal Aid/Human Rights Office-Power Disconnection, June 8-13, 2016, 7:00am-5:00pm

CAW Student Centre-New Food Service Installation, June 1-August 30, 2016, 8:00am-5:00pm 

Alumni Hall/Clark Residence I and II, Fibre Optic Cable Update, June 26, 2016, 7:00am-6:00pm

Campus Wide Steam Outage, June 24, 2016 - June 27, 2016, 12:00pm - 10:00am

Campus Wide Power Outage, June 26, 2016, 6:00am - 6:00pm

May 2016

Lambton Tower-Emergency Bearing Replacement, May 30, 2016, 9:30am-3:00pm

Biology Building-New Steel Door Installation (May Be Noisy from Drilling), May 24-June 2, 2016, 6:00am-8:00pm

Education Building-Elevator Out of Service, April 29-June 30, 2016, 8:00am-4:00pm

Health Education Centre-Emergency Generator Exhaust Connections Installation, May 24-27, 2016, 6:00am-6:00pm

Medical Education Building-2nd Floor and Basement Mechanical Room Updates, May 30, 2016, 7:30am-4:30pm

Chrysler Hall Tower-Air Distribution System Investigation, May 30, 2016, 8:30am-4:00pm

Erie Hall/Lambton Tower-Washrooms Upgrade Project, Type II & Type III Asbestos Abatement, May 9-June 2, 2016, 7:30am-11:00pm

Energy Conversion Centre-Asbestos Abatement, May 31-June 3, 2016, 7:30am-4:30pm

Community Legal Aid/Human Rights Office-Abatement of Hazardous Materials, May 31-June 10, 2016, 7:00am-5:00pm

Pitt Ferry Building-Building Switchgear Inspection, May 29, 2016, 8:00am-4:00pm

Medical Education Building-Fire Alarm System Updates, May 26-27, 2016, 7:30am-12:00pm

Law Building-Emergency Leak Repair, May 25, 2016, 8:30am-11:00am

Centre for Engineering Innovation-Installation of Data Cable, May 27, 2016, 8:30 am - 4:30 pm

Health Education Centre-Women's Washroom Access on 1st & 2nd Floor, May 24, 2016 - May 27, 2016, 6:00 am - 6:00 pm

Law Building-Fans Insulation Completion, May 24, 2016, 7:00 am - 11:00 am

Biology Building-HVAC and Fumehood Exhaust Shutdown, May 24, 2016, 7:00am-7:00pm

Chrysler Hall Tower-Emergency Bearing Replacement, May 19, 2016, 9:30am-3:00pm

MacDonald Hall-Intrusive Designated Substance Assessment, May 19, 2016, 8:00 am - 4:00 pm

Biology Building-New Steel Door Installation (May be Noisy from Drilling), May 24-27, 2016, 6:00am-8:00pm

Erie Hall/Lambton Tower-HVAC Shutdown/Type II Asbestos Abatement Work, May 24-June 3, 2016, 7:30am-4:30pm

Innovation Centre/Parking Garage-Fire Alarm Updates-May 25, 2016, 7:30 am - 4:30 pm

Lambton Tower-Emergency Fan Shutdown, May 13-23, 2016, 10:00am-2:00pm

Erie Hall/Lambton Tower-Men's & Women's Washrooms Shutdown, May 17-September 16, 2016, 7:30am-4:30pm

Medical Building Lot "W"-No Pay & Display Parking Available, May 20, 2016, 7:00am-2:00pm

Centre for Engineering Innovation/Chrysler Hall North-Catch Basin Repairs, May 13-16, 2016, 8:00am-4:00pm

Pitt Ferry Building-Fire Protection, May 27, 2016, 10:30am-2:30pm  

Pitt Ferry Building-Emergency Generator/Emergency Lighting, May 27, 2016, 8:00am-12:00pm

Pitt Ferry Building-Plumbing, May 30, 2016, 8:00am-2:30pm

Pitt Ferry Building-Building Envelope, May 30, 2016, 8:00am-2:30pm

Pitt Ferry Building-Elevator, May 30, 2016, 1:30pm-3:00pm

Pitt Ferry Building-Sprinkler System, June 3, 2016, 8:00am-12:00pm

UPDATE: Education Building-Elevator Out of Service/Loud Machinery, April 29-May 27, 2016, 8:00am-4:00pm

Chrysler Hall Tower-West Elevator Out of Service, May 18-20, 2016, 9:00am-4:00pm

Law Building-Fans, May 13, 2016, 10:00am-2:00pm

Chrysler Hall North/Chrysler Hall South-Inspection of Shelf Angle, Soffit and Fascia, May 19-20, 2016, 7:00am-5:00pm

Biology Building-Electrical Power, May 14, 2016, 8:00am-4:00pm

Energy Conversion Centre-Window Replacement, May 13, 2016, 8:00am-4:00pm

Erie Hall-Fire Alarm System Updates, May 12, 2016, 8:30am-4:00pm

Assumption Hall-Domestic Hot Water Shutdown, May 13, 2016, 9:30am-2:00pm

Assumption Hall-Fire Suppression System Inspection, May 17, 2016, 1:00pm-4:00pm

Erie Hall/Lambton Tower, Fire Alarm System, May 9-20, 2016, 7:30am-3:30pm

Law Building-Fans Shutdown, May 6, 2016, 11:00am-4:00pm

St. Denis Fieldhouse & Human Kinetics-Intermittent Fan Operation, May 9-13, 2016, 7:00am-3:00pm

2629 Riverside Drive (Building & Garage)-Access to Building and Garage, May 10-September 30, 2016, 7:00am-5:00pm

Energy Conversion Centre-Chimney Repair, May 9-13, 2016, 7:00am-3:00pm

Pitt Ferry Building-Exterior Window Washing, May 9, 2016, 7:00am-4:00pm

Assumption Hall-Assumption University Park Lot/Dead Tree Removal, May 10-11, 2016, 7:00am-5:00pm

Erie Hall/Lambton Tower-Type II and Type III Asbestos Abatement, May 9-18, 2016, 7:30am-11:00pm

Pitt Ferry Building-Heating/Ventilation, May 6, 2016, 7:00am-4:00pm

Chrysler Hall Tower/Chrysler Hall South-CHT South Entrance Door/CHS North Entrance Door/Southeast Stairs to Deck, May 6, 2016, 8:30am-4:30pm

Welcome Centre-Fire Alarm/Sprinklers/HVAC Units, May 6-7, 2016, 7:00am-4:00pm

Essex Hall-Construction of New Gate Along Patricia Avenue, May 7-August 31, 2016, 7:00am-5:00pm

MacDonald Hall - Removal of Parking Lot and Addition of New Drop Off Area, May 3 - July 31, 2016, 7:00am-5:00pm

REVISED DATE: Law Building-Fans, May 2-4, 2016, 7:00am-3:00pm

REVISED: Pitt Ferry Building-Building Envelope, May 4, 2016, 8:00am-4:00pm

REVISED: Pitt Ferry Building-Plumbing, May 4, 2016, 8:00am-4:00pm

Centre for Automotive Research & Education-Fire Alarm Inspection, May 4-5, 2016, 8:30am-4:30pm

CAW Student Centre/Vanier Hall- Fire Suppression System Inspections, May 4, 2016, 8:00am-4:00pm

Odette School of Business/Law Building-Fibre Optic Cable Upgrades, May 9-29, 2016, 8:30am-4:30pm

Campus Wide Switchover - Heating to Cooling Mode, May 1, 2016 - October 17, 2016, 12:00pm - 10:00am 

Pitt Ferry Building, Sprinkler System/Fire Protection Back Flow, May 6, 2016, 12:00pm - 4:00pm

Odette School of Business/Law Building/Service Tunnel-Fibre Optic Cable Upgrades, May 1- 20, 2016, 8:30am-4:30pm

April 2016

University Computer Centre-Steam Meter Installation, April 28-May 2, 2016, 7:00am-4:00pm

Essex Hall - Chemical Control Centre-Cold Water/Vacuum, April 28, 2016, 7:30am-8:30am

Law Building-Fans, April 26-29, 2016, 7:00am-3:00pm

Centre for Engineering Innovation-Smoke Exhaust System, April 28, 2016, 5:00pm-7:00pm

MacDonald Hall - Land Survey, April 27-29, 2016, 7:00am-5:00pm

Parking Garage-Column Repairs, April 25-29, 2016, 7:00am-4:00pm

DATE REVISED: Memorial Hall-Fire Alarm Updates, April 25, 2016, 7:30am-12:00pm

Memorial Hall-Fire Alarm Updates, April 22, 2016, 7:30am-12:00pm

DATE REVISED: Chrysler Hall Tower-Air Handling Units Exhaust, April 24-26, 2016, 8:00am-3:00pm

Assumption Hall-Fire Alarm System Updates, April 21, 2016, 7:00am-12:00pm

Education Building-Elevator Out of Service, April 29-May 27, 2016, 8:00am-4:00pm

Joyce Entrepreneurship Centre/Parking Garage-Fire Alarm Upgrades, April 27, 2016, 7:30am-4:30pm

Dillon Hall-Main Entrance Sidewalk Access, April 25-30, 2016, 7:30am-4:30pm

Chrysler Hall Tower-Air Handling Units Exhaust, April 20-22, 2016, 8:00am-3:00pm

Odette School of Business-Access to Loading Dock, April 19-26, 2016, 7:00am-5:00pm

Chrysler Hall North/Chrysler Hall South - Window Replacement, April 19-21, 2016, 8:00am-4:00pm

Assumption Hall - Fire Alarm System Updates, April 19, 2016, 8:00am-11:00am

Chrysler Hall North/MacDonald Hall/Medical Education Building-Installation of Fence, April 18, 2016-May 6, 2016

University Computer Centre-Replace & Relocate Frozen Steam Flow Meter, April 18-21, 2016, 8:00am - 4:00pm

Chrysler Hall Tower - West Elevator Out of Service, April 13-14, 2016, 9:00am - 4:00pm

Pitt Ferry Building-Backflow Prevention Testing, April 22, 2016, 11:00am-4:00pm

Pitt Ferry Building, Plumbing - April 28, 2016, 8:00am - 4:00pm

Pitt Ferry Building, Building Envelope, April 28, 2016, 8:00am - 4:00pm

Pitt Ferry Building, Emergency Generator/Emergency Lighting, April 29, 2016, 8:00am - 12:00pm

Pitt Ferry Building, Fire Protection, April 29, 2016, 10:30am - 2:30pm

Chrysler Hall Tower-Air Handling Units Shutdown, April 14-15, 2016, 3:00pm-7:00am

Leddy Library (West)/Leddy Library (East) Main Building- Fire Alarm System/HVAC Equipment, April 13, 2016, 8:00am-10:00am

Tunnel/Central Refrigeration Plant-Chilled Water Piping Repair, April 11-16, 2016, 7:00am - 3:00pm

Assumption Hall - Domestic Cold & Hot Water Shutdown, April 11, 2016, 7:00am-10:00am

Pitt Ferry Building - Plumbing, April 5, 2016, 8:00am - 4:00pm

Centre for English Language Development-Install Data and Telecommunications Wiring, April 4-5, 2016, 8:00am-4:30pm

Medical Education Building/Health Education Centre-Fire Alarm Inspection/Survey, April 5-6, 2016, 9:00am-4:00pm

Pitt Ferry Building - Sprinkler System, April 7, 2016, 8:00am-4:00pm

Pitt Ferry Building - Emergency Generator/Emergency Lighting, April 1, 2016, 8:00am-12:00pm

Pitt Ferry Building - Fire Protection, April 1, 2016, 11:30am-4:00pm

March 2016

Essex Hall - Domestic Hot and Cold Water Shutdown, March 29, 2016, 12:00pm - 4:00pm

Vanier Hall - Domestic Hot Water Shutdown, March 24, 2016, 2:00pm-4:00pm

Essex Hall - Fume Hood Repair, March 29-31, 2016, 1:00pm -3:00pm

Essex Hall - North Wing Building-Shutdown Fans for Asbestos Abatement, March 24, 2016, 8:00am-12:00pm

Centre for English Language Development - IT Closet/Mechanical Room, March 28, 2016, 8:00am-4:30pm

Central Refrigeration Plant-Cooling Water Pump, March 23, 2016, 9:00am-3:00pm

Leddy Library (East) Main Building-Fire System Testing/HVAC System-March 23, 2016, 8:00am-5:00pm

Essex Hall/Chemical Control Centre, Fire Alarm System/HVAC-March 22, 2016, 8:00am-4:00pm

University Computer Centre-HVAC Units, March 22, 2016, 8:00am-4:00pm

Chrysler Hall North - Access to Sunset Avenue Disruption, March 23, 2016-April 1, 2016, 7:00am-5:00pm

SAFETY ADVISORY-The Safe Disposal of Appliances Containing Ozone Depleting Refrigerants

Pitt Ferry Building-Heating/Ventilation, March 23, 2016, 7:00am-4:00pm

Odette School of Business/St. Denis Fieldhouse - Video Surveillance Repairs, April 4-8, 2016, 8:00am-4:00pm

Human Kinetics-Heating, March 21-23, 2016, 7:00am-4:00pm

Medical Education Building/Health Education Centre-Fire Alarm Inspection & Survey, March 21-22, 2016, 8:00am-4:00pm

DATE REVISED: Erie Hall/Lambton Tower - Domestic Hot & Cold Water Shutdown, March 20, 2016, 7:30am-1:30pm

Odette School of Business - Fire Alarm System Inspection & Survey, March 16-17, 2016, 8:00am-4:00pm

Erie Hall and Lambton Tower - Domestic Hot and Cold Water Shut Down, March 19, 2016, 7:30 am - 1:30 pm

Leddy Library (East) Main Building and Leddy Library West Wing- Upgrades to existing locks, March 15 -31, 2016, 7:30 am - 4:30 pm

Erie Hall/Lambton Tower - Fire Alarm Updates, March 14, 2016, 7:30am-2:00pm

Chrysler Hall South - Emergency Domestic Cold Water Shutdown, March 9, 2016, 8:00am-9:30am

Erie Hall/Lambton Tower-Erie Hall Washrooms Upgrade Project/Type II Asbestos, March 9-24, 2016, 7:30am-4:30pm

Chrysler Hall Tower-Building HVAC System/Type II Asbestos Work, March 11-13, 2016, 5:30pm - 4:00pm

CAW Student Centre-Security Cameras/Emergency Phones Installation, March 21-April 11, 2016, 7:00am-5:00pm

Chrysler Hall Tower - Renovations East End 3rd Floor, March 8, 2016-May 13, 2016, 8:00am-4:00pm

Pitt Ferry Building - Electrical, March 17, 2016, 8:00am-12:00pm

Lambton Tower/Medical Education Building- Heating Ventilation, March 28-April 4, 2016, 7:00am-4:00pm

Jackman Dramatic Art Centre/Innovation Centre- Heating Ventilation, March 21-28, 2016, 7:00am-4:00pm

Essex Hall/Essex Hall (Chemical Control Centre) - Heating Ventilation, March 14 - 21, 2016, 7:00am-4:00pm

Biology/Dillon Hall - Heating Ventilation, March 7-11, 2016, 7:00am-4:00pm

Pitt Ferry Building - Fire Extinguishers Inspection, March 7, 2016, 8:00am-4:00pm

Pitt Ferry Building - Emergency Generator, March 8, 2016, 8:00am-4:00pm

Pitt Ferry Building - Sprinkler System Inspection, March 9, 2016, 8:00am-4:00pm

Erie Hall/Lambton Tower-Erie Hall Washrooms Upgrade Project, March 2, 2016 - September 16, 2016, 7:30am-4:30pm

February 2016

Pitt Ferry Building - Emergency Phone Installation, February 24 - 25, 2016, 8:00am - 4:00pm

Pitt Ferry Building - Elevator Out of Service - February 26, 2016, 1:00pm - 4:00pm 

Essex Hall EH - Domestic Cold Water Shut Down, February 18, 2016, 3:00 pm - 8:00 pm

Centre for Engineering Innovation CEI - Preventative Maintenance on Heating and Ventilation Systems, February 22 - March 4, 2016, 7:00 am - 4:00 pm

Welcome Centre - Fire Alarm System, February 29, 2016, 8:30am-10:30pm

Pitt Ferry Building - Fire Protection Inspections, February 26, 2016, 1:00pm - 4:00pm

Pitt Ferry Building - Emergency Generator/Emergency Lighting, February 26, 2016, 8:00am - 12:00pm

Assumption Hall - Storm Piping System Upgrade, February 16, 2016 - May 30, 2016, 7:00am-5:00pm

REVISED: Innovation Centre - Fire Alarm Upgrades, February 1, 2016 - March 4, 2016, 8:30am-4:30pm

Law Building - Domestic Cold Water Shutdown, February 19, 2016, 8:00am-4:00pm 

Great Lakes Institute of Environmental Research GLIER - Roof Erecting Guarding, February 16 - 18, 2016 7:00 am - 12:00 pm

Biology - Fire Alarm Testing Modifications, February 12, 2016, 7:45am-8:30am

Dillon Hall DH - Elevator Shutdown, April 25 - 29, 2016, 8:30 am - 4:30 pm

Chrysler Hall North, South and Tower - Heating & Ventilation Interruptions, February 8 -18, 2016, 7:00 am - 4:00 pm

Odette School of Business - Domestic Hotwater Shutdown, February 5, 2016, 8:00am-4:00pm

Welcome Centre - Multipurpose room, 1st floor-work on the audio/visual system, February 8-10, 2016, 7:00 am - 5:00 pm

Biology-Vacuum Shutdown, February 5, 2016, 9:30am-12:00pm

Great Lakes Institute of Environmental Research - Emergency Repair System Heating, February 6, 2016, 7:00am-12:00pm

Welcome Centre - Installation of exterior lighting, February 5 - 8, 2016, 7:00 am - 5:00 pm

Odette School of Business - Domestic Hotwater Shutdown, February 2, 2016, 2:30pm - 4:00pm

Campus Wide Power Outage - May 14, 2016, 6:00am - 6:00pm

University Computer Centre - New Call Centre Renovations, February 5 - March 4, 2016, 8:00am - 5:00pm

Law Building - Water Main Break Repaired, February 1, 2016, 2:00pm

Law Building - Water Main Break, February 1, 2016, 10:00am - 6:00pm

Innovation Centre/Parking Garage -Fire Alarm Upgrades, February 1 - March 4, 2016, 8:30am-4:30pm

January 2016

Chrysler Hall North - Domestic Hot Water Shutdown, January 28, 2016, 8:00am - 10:00am

Windsor Star Building - Microwave Breakers, January 25, 2016, 7:00am-4:00pm

Central Refrigeration Plant - Condenser Water Piping, January 25-29, 2016, 7:00am-4:00pm

Biology - Heating, January 25-29, 2016, 7:00am-4:00pm

Lambton Tower Elevators Back in Service - January 22, 2016

Welcome Centre - Heating, January 21, 2016, 7:00am-4:00pm

Centre for Engineering Innovation - Fire Alarm Testing, January 21, 2016, 8:30am-4:30pm

Essex Hall - Lab 394-3 Renovations, January 18-22, 2016, 8:00am-4:00pm

Dillon Hall - Fire Alarm Shutdown, January 18, 2016, 8:00am -4:00pm

Lambton Tower Elevator Out of Service until further notice.

Chrysler Hall South Elevator Out of Service until further notice.

Education Gym - Elevator Back in Service, January 11, 2016

Cartier Hall - Elevator Back in Service, January 11, 2016

Dillon Hall - Sprinkler System Installation/Fire Alarm Shutdown - January 13, 2016, 8:00am-4:00pm

University Computer Centre - Data Drops Installation, January 11-12, 2016, 7:00am-4:00pm

Lambton Tower - East Elevator Out of Service

Biology Building - Emergency Shutdown Asbestos Enclosure, January 8, 2016, 6:00am-10:00am

Lambton Tower - West Elevator Out of Service, January 7, 2016, 2:00pm-6:00pm

Education Gym - Elevator Out of Service

December 2015

Law Building-Heat Shutdown, December 19, 2015 - January 4, 2016, 6:00am - 11:00am

Education Building-Security Upgrades, December 15, 2015 - December 12, 2016, 7:30am-4:30pm

Biology-Ductwork Capping, December 21, 2015, 8:30am-5:00pm

Essex Hall-Steam Leak, December 21, 2015, 6:00am-12:00pm

Chrysler Hall Tower-Fire Alarm System, December 21, 2015, 8:00am-3:30pm

Essex Hall - Floor Drain Repair, December 15, 2015, 10:00am - 4:00pm

Innovation Centre - Install Fire Alarm Pull-Station, December 16-21, 2015, 8:00am-4:00pm

Law Building - HVAC Repair, December 21, 2015 to January 3, 2016, 6:00am - 11:00am

Human Kinetics - HVAC Repair, December 15-16, 2015, 7:00am - 4:00pm

Chrysler Hall North, Chrysler Hall South, Chrysler Hall Tower - Hotwater Shutdown, December 10, 2015, 8:00am-10:00am

CAW Student Centre/Jackman Dramatic Art Centre/Health Education Centre - Renovations, December 21, 2015 - June 1, 2016, 7:00am-5:00pm

Katzman Lounge, Vanier Hall - Painting, December 17-31, 2015, 7:00am-5:00pm

Assumption Hall - Domestic Hotwater Shutdown, December 8, 2015, 8:00am - 10:00am

Odette School of Business - Heat Pump Replacement, December 12-13, 2015, 6:00am-4:00pm

Pitt Ferry Building - IR Scan/Ground Grid Testing - December 8-9, 2015, 12:00pm-8:00pm

LeBel Building-Natural Gas Shutdown, December 9, 2015, 9:00am-12:00pm

Essex Hall - Condensate Leak, December 5-9, 2015, 8:00am-12:00pm

Essex Hall - Electrical Panel Installation, December 4, 2015, 7:30am-9:00am

Biology-Renovations/Asbestos Abatement, December 2, 2015 to September 30, 2016, 7:00am-5:00pm

Essex Hall - Service Shutdown, December 15-16, 2015, 8:00am-4:00pm

Welcome Centre - Commissioning of the Heating System, December 8-9, 2015, 7:00am-5:00pm

Essex Hall - Asbestos Abatement, Type II, December 10-11, 2015, 4:30pm-10:30pm

Centre for Engineering Innovation (CEI)-Commission the Smoke Exhaust System, December 7, 2015, 8:00am-5:00pm

Vanier Hall/MacDonald Hall/Laurier Hall - Steam Leak Repair, December 5, 2015, 4:00am-10:00am

Leddy Library (West Wing)/Energy Conversion Centre - Fire Suppression System Inspection- December 2, 2015, 8:00am-4:00pm

Essex Hall-Chemical Control Centre/University Computer Centre - Fire Suppression System Inspection- December 1, 2015, 8:00am-4:00pm

Chrysler Hall Tower - Fire Dampers & Actuators Installation, December 4-5, 2015, 7:30am-1:00pm

Chrysler Hall Tower CHT - Repairs to Janitors Closet Faucets on 4th Floor, December 2, 2015, 7:30 am - 10:00 am

November 2015

Centre for Engineering Innovation - CEI, Emergency Exit Door damaged and not accessible, November 26, 2015 - February 29, 2016 6:00 am - 7:00 pm

Essex Hall - Lab 287 Renovations, December 1, 2015 - January 30, 2016, 8:00 am to 4:00 pm

Lambton Tower LAM - Low water pressure in washrooms, November 26 - December 22, 2015, 6:00 am - 6:00 pm

Biology BIO and Essex Hall EH - Equipment Moves, November 25 - 27, 8:30 am - 4:30 pm

Maintenance Building - Partial Heating, November 25, 2015, 7:00am - 7:00pm

Essex Hall - Center Elevator Out of Service, November 24, 2015-February 29, 2016, 6:00am-6:00pm  

Erie Hall/Lambton Tower - Washroom Upgrades Project, November 28, 2015, 7:00am-7:00pm

Leddy Library (East) Main Building - Replacement of Concrete Approach Pad, November 23-December 3, 2015, 6:30am-6:00pm

Law Building Upgrades, August 24, 2015-November 30, 2015, 8:00am - 5:00pm

Human Kinetics - Heating & Cooling, November 17-19, 2015, 6:00am - 7:00pm

Chrysler Hall North/Chrysler Hall Tower-Elevator Out of Service, November 19, 2015, 8:00am - 5:00pm

Essex Hall/Chrysler Hall Tower, Elevator Out of Service, November 18, 2015, 8:00am - 5:00pm

Dillon Hall/Memorial Hall - Building Power Shutdown, November 19, 2015, 6:00am - 7:45am

Lambton Tower - Elevator Out of Service, November 17-25, 2015

CAWSC Freight Elevator Out of Service, November 17, 2015, 9:00am - 4:00pm

HK Penthouse - Heating and Cooling, November 17, 2015 from 6:00am - 6:00 pm

167 Ferry Street - Heating and Cooling, November 14-15, 2015, 12:00pm - 6:00pm

Biology - Elevator Out of Service, November 16, 2015, 9:00am-7:00pm

University Computer Centre - Camera Installation, November 17-19, 2015, 7:00am-5:00pm

Inspection for Facilities Survey Designated Substances, November 16 - December 21, 2015, 8:00am - 5:00pm

Chrysler Hall Tower - Deck on South Side Closed Due to Cracked Window, November 12 - 30, 2015, 3:00pm - 4:00pm

GLIER - Electrical Upgrade, November 16, 2015, 7:00am - 8:00am

GLIER – Fire Alarm System, November 12, 2015, 7:30am-9:00am

Dillon Hall - Building Power Shutdown, November 17, 2015, 6:00am-7:45am

Leddy Library (East) Main Building - Washroom Upgrades, November 12, 2015, 8:30am-12:00pm